Status at 2026-10-11

Added since 2026-10-05: the W-* wallet and demo-slice lane (issues

65–#69, opened 2026-10-05) had no backlog entry at all — five tasks, three

owners and the whole PLAN-0004 application plan, tracked only in GitHub. A lane that exists only as issues is invisible to the one file that is supposed to be the durable index. They are now §Wallet and demo slice below.

Ids: the 2026-09-28 decisions are now MD-1 … MD-7, not D-n (GLOSSARY-0001; DECISIONS-0001 item 27). D0 … D10 deliverables are unchanged, which is the point of the rename.

In review: mofn#82 (DECISIONS-0001 v0.2.0, the MD-1…MD-7 transcription), mofn#83 (ADR-0002 proposed, T-029d), library#65 (the rename + FX-1 mandate), library#66 (gaps.md refresh). T-029e closes with #82.

Status at 2026-10-05 — I1 closes Oct 14

This file had not moved since 2026-09-22. Brought up to date from the repos, merged PRs and the 2026-09-28 decisions (MD-1…MD-7, project/meetings/).

At risk for Oct 14 (I1): - D3 research reports (T-025–T-027) — not started. No student report exists in research/. MD-4 says draft them from survey R-001 (§2/§4 mechanism, §5–§8 uptake); the material is there, the reports are not. - D1 construction method (T-020) — library/docs/construction.md last edited 2026-09-16. - Library quality (T-024) — 280 records, but 16 written and 264 unwritten scaffolds (library#45). The count was reading as progress. - Lane issues mofn#13, #14, #23 — no activity since 2026-09-21/22.

Overdue sponsor-side and agent actions: ADR-0002 draft (Claude, was Oct 2); DECISIONS-0001 T1-A closure (Claude); Product Spec GAP-6 dates (Paul).

Process: every merge needs one approval and enforce_admins is off in both repos, so the sponsor is the only path to main. Neither student has reviewed the other's PRs (0 reviews). See T-006c, T-006d.

Pending sponsor decision: library#42 narrows FX-1 from "every spec record a PR moves past stub" to "every record a PR extracts" (summaries held to the summary bar). Accept or keep #32's rule — L-035.


I0 — Harness · Sep 16–30 · D0

id task del own sz status
T-001 ~~Create GitHub org m-of-n~~ — done; DEC-001 accepted D0 PL S done
T-002 ~~Create mofn and library repos~~ — done, both public and pushed D0 PL S done
T-003 Fall 2026 deliverables — definition of done. PROC-0004, aligned to D0–D10. Parent issue mofn#28 with sub-issues D0–D10 all L doing
T-003x ~~Branch protection~~ — done; residual settings are T-006c D0 S1 S done
T-004 CODEOWNERS → /spec/ and /project/ to PL; both students on the catch-all D0 S1 S done
T-005 ~~DCO check in CI~~ — done, both repos D0 S1 S done
T-006 ~~Issue + PR templates; labels; milestones~~ — done D0 S2 M done
T-006a ~~Repo admin for both students~~ — done, both repos and the org D0 PL S done
T-006b Decide faculty access for Mario Lin (read? admin?) — not yet a collaborator or invitee D0 PL S todo
T-006c Turn on enforce_admins now a second reviewer exists — still off in both repos (2026-10-05) D0 PL S todo
T-006d Students review each other's PRs — 0 cross-reviews to date; every merge currently waits on the sponsor D0 S1+S2 S todo
T-007 ~~bin/validate-archdoc in CI~~ — done D0 S1 M done
T-008 ~~MkDocs Material site deploying to Pages~~ — done; live at m-of-n.github.io/mofn D0 S2 M done
T-009 ~~library wired as submodule; bin/lib-sync working~~ — done D0 S1 S done
T-010 ~~bin/wt worktree helper; document in CONTRIBUTING~~ — done D0 S1 S done
T-011 ~~Publish draft planning docs to Pages~~ — done D0 S2 S done
T-012 Architecture development — market research, technology background, bibliography, base design of both protocols and the application. Scope extends beyond the student project. Deliverable: the architecture specification. Iterated in-issue. Inputs so far: ARCH-0002, survey R-001, wallet survey R-002, cipher suite R-0003 (mofn#60) — PL XL doing
T-012x ~~design-log/ opened~~ — done; DL-0001 and DL-0002 written D0 PL S done
T-013 Agree and commit the cut order (PLAN-0001 §12) — mofn#7, no discussion yet D0 all S todo

I1 — Library & research · Oct 1–14 · D1 D2 D3

id task del own sz status
T-020 D1 v0.1 — construction best practice (library/docs/construction.md) — at risk: last edit 2026-09-16; FX-1 (docs/extraction.md) now carries much of it D1 S2 L doing
T-021 ~~Seed 10 records by hand to prove the schema~~ — done D2 S2 M done
T-022 Ingest adapters verified for each type: pdf, url, ietf, xlsx, md, book, repo, consortium, hierarchy D2 S2 M doing
T-023 Shelfmark: converge requirements, then schema. No data merger. Write the requirements diff D2 PL M todo
T-024 Library to ~40 records across the topics — count met (280), quality not: 16 written, 264 scaffolds. Fill tracked in library#45 D2 S2 L doing
T-025 Report: context — not started; draft from survey R-001 §1–§3 (MD-4) D3 S1 L todo
T-026 Report: mechanism — the evidence base for DEC-002 and DEC-004 — not started; R-001 §2/§4, plus the RFC 8785 R-O-05 analysis in library#46 D3 S1 L todo
T-027 Report: uptake/applications — incl. SPKI and PICS failure-to-adopt — not started; R-001 §5–§8 D3 S2 L todo
T-028 Topic notes answered for namespace-governance, canonical-encoding — canonical-encoding in review (library#46); 3 of 17 topics answered overall D3 PL/S1 M doing
T-029a Schema scenarios (3–5, incl. email delegation) and Product Spec personas, GAP-1 (MD-1) D3 S1+S2 M todo — was due Oct 5
T-029b Product Spec, PLAN-0002 v0.2 — GAP-4 real sketches (Ndewedo, Oct 14), GAP-6 course dates (PL) — PL+S2 M doing
T-029c Confirm Tauri for the wallet GUI (MD-7) before GUI work starts D8 S2 S todo — Oct 14
T-029d ADR-0002: accept P2, P3, P5, P6 provisionally (MD-2) — Claude→PL M overdue (was Oct 2)
T-029e Close T1-A in DECISIONS-0001 citing MD-1 — Claude S overdue

I2 — Schema + DEC-002 · Oct 15–28 · D4 D5

id task del own sz status
T-030 WP1 — encoding-neutral schema for ARCH-0001 §4 logical types D4 S1 L todo
T-031 Fixtures: NameCert, AuthzCert with threshold subject, ArtifactStatement — in option 5 (MD-3) plus the option-2 comparison D5 S1 L todo
T-032 Score option 5 against option 2 incl. namespace governance (MD-3 narrowed DEC-002 to these) — needs library#39 Tier 1 extracted first D5 S1 M todo
T-033 ADR for DEC-002 (ADR-0001 is taken by key-relative naming) — accepted; ARCH-0001 status updated + changelog D5 PL M todo
T-034 Canonicalization idempotence + round-trip tests in CI D5 S2 M todo
T-035 ~~Resolve R-M-12: requirement row, or ARCH-0002?~~ — ARCH-0002, accepted as P1 via ADR-0001 — PL M done

I3 — Reduction · Oct 29–Nov 11 · D6 · DEMO FLOOR

id task del own sz status
T-040 Name resolution: Name → KeyId via NameCert chains (§4.3 step 1) D6 S1 L todo
T-041 5-tuple reduction: tag ∩, validity ∩, delegation (§4.3 step 2) D6 S1 L todo
T-042 Minimal tag profile — opaque bytes + bytes-equal (DEC-004 minimum) D6 S1 M todo
T-043 k-of-n threshold subjects, keys only, no nesting D6 S2 L todo
T-044 Statement acceptance (§4.3 step 3), kept separate from reduction D6 S2 M todo
T-045 Verifier output reports the three separately (R-O-06) D6 S2 M todo
T-046 Published test vectors under spec/vectors/ D6 S1 M todo
T-047 Demo: chain reduces; break a link; verifier explains which and why D6 all M todo

I4 — Mappings & app · Nov 12–25 · D7

id task del own sz status
T-050 WP2 — MAP-0001 SPKI/SDSI S-expression ↔ native D7 S1 L todo
T-051 WP3 — MAP-0002 in-toto Statement ↔ ArtifactStatement D7 S1 L todo
T-052 Round-trip a real SLSA v1.1 provenance from a public release D7 S1 M todo
T-053 Record interchange losses in the §6 matrix (R-I-01) D7 S1 M todo
T-054 App packaging — single-file zipapp D8 S2 M todo
T-055 Demo: valid-but-unauthorized key → distinct verdict D7 S2 M todo

I5 — Polish · Nov 26–Dec 4 · D8 D9 D10

id task del own sz status
T-060 App download live on Pages, with install docs D8 S2 M todo
T-061 Market & applications research D9 PL/S2 L todo
T-062 LIMITATIONS.md final — what this does not prove D10 all S todo
T-063 Final report D10 all L todo
T-064 Demo rehearsals ×3 D10 all M todo

Wallet and demo slice — W-* · issues #65–#69

Opened 2026-10-05 against PLAN-0004 and parent #31 (T-003.5, the demo floor). Tracked here from 2026-10-11; before that they existed only as issues. W-1 is the engine everything else calls — nothing in this lane starts before it runs.

id task issue del own sz status
W-1 Wallet engine v0 — mofn CLI over a local wallet/ (roots/ keys/ domains/ statements/); init, key gen (private key 0600, encrypted at rest, passphrase prompted, never an argument), root add, make, check printing the six-line verdict. Signature checking moves inside reduction — reduce stops trusting its inputs #65 D6 S1 XL todo — Oct 28
W-2 Second domain — one-page scenario per MD-1 target (supply chain, archives/library) incl. the fail-authorization case and three personas; archives domain file v0 (record-review, renderings table, --lang es); five-view sketches replacing Product Spec §6.5 #66 D6/D8 PL L todo — Oct 14, then Nov 25
W-3 Delegation with short expiry — may-speak chains in reduce, intersecting topic and validity; expired or out-of-topic → authorization FAIL naming the broken link. Short expiry is the revocation mechanism; there is no revocation list #67 D6 PL L todo — Nov 11
W-4 Weekly demo slice owner — grow and run demo/slice.sh every Monday, post the output on the issue. Three cases minimum: green, authorization FAIL, integrity FAIL #68 D6 S2 M doing — weekly
W-5 Mac GUI — local desktop app (not a web server) for signing and verify/validate display with attribute associations; calls the W-1 engine, reimplements no crypto. Sign and Verify screens first #69 D8 S2 L todo — Dec

Overlap to resolve. W-1 and W-3 restate T-041/T-044/T-045 (reduction, statement acceptance, separated verifier output) as application work, and W-2 restates T-029a/T-029b. They are the same deliverables seen from the application side. Either the T- rows or the W- rows should become pointers, not both live — otherwise I3 is double-counted. Flagged, not resolved: it is a planning call, not a transcription.

Library build-out — from library#1 and sponsor direction 2026-09-21

L- tasks run in m-of-n/library. Most are I1; they gate #13 and #14.

id task src own sz status
L-001 ~~summary.md primary; distilled.md = requirements extraction~~ #1.1 — L review
L-002 ~~status: stub for references that bear on nothing yet~~ sponsor — S review
L-003 ~~Controlled tag vocabulary: subject / body / role~~ #1.6,10 — M review
L-004 ~~maturity on RFC 2026 levels~~ sponsor — S review
L-005 ~~OKF alignment — YAML front matter, documented extensions~~ #1.11,12 — M review
L-006 ~~implementations field — open source + commercial~~ #1.3 — S review
L-007 ~~research/ for archived method research~~ sponsor — S review
L-010 ~~Fill out the 9 existing records~~ — superseded by library#45 (264 scaffolds) #1.2 S2 L parked
L-011 NIST cryptographic algorithms — summarised records, not stubs (sponsor 2026-09-22). Document set below; expanded scope in library#8; Ndewedo's library#42 in review #1.4 S1 L review
L-012 ~~NIST digital signature specifics~~ — folded into L-011 #1.2 S1 — done
L-013 Attestation specifications sweep — RATS, EAT, CoRIM, TPM, Confidential Computing — ingested by the survey (topic device-attestation, 26 records), not written (#45) #1.2,7 S1 L doing
L-014 Trust management publications — deep research gather #1.7 S2 L todo
L-015 Implementation search across all records — open source + commercial #1.3 S2 M todo
L-016 Organised bibliography for review; confirm the schema supports it #1.6 S2 M todo
L-017 Applicability review pass over all records after first summarisation #1.8 PL M todo
L-018 Define ingestion scope: standards, specs, recommendations, white papers, sites, repos #1.10 PL S todo
L-019 Archive the method research behind docs/construction.md — sources were discarded sponsor S2 M todo
L-020 ~~Multi-agent ingestion plan~~ — done: PROC-0002, and FX-1 docs/extraction.md for spec records #1.5 PL M done
L-021 mofn/research/ — D3 reports with sources.md and searches.md sponsor S1 S todo
L-022 Promote recurring free tags into schema/tags.yaml (rule of three) #1.6 S2 S todo
L-030 ~~FX-1 full extraction standard — enforced in CI~~ — library#32 sponsor Claude M done
L-031 FX-1 extraction of the CBOR/COSE set, ranked — Tier 1 needed for D5 by Oct 28 library#39 S1 XL todo
L-032 SCITT full extraction (#30 merged as summaries only) library#40 S1 L todo
L-033 Fill the 264 unwritten scaffolds, batched by topic library#45 S2 XL todo
L-034 YAML reader block scalars, scaffold inventory, duplicate detection library#43/#35/#45 → #48 Claude M review
L-035 Sponsor decision: accept library#42's FX-1 carve-out (summaries held to the summary bar), or keep #32's rule library#42 PL S todo
L-036 First student FX-1 extractions — RFC 9804, RFC 8785; independent review posted, one item open (9804 verify pass not independent) library#46 S2 L review

L-011 — the NIST set

Sponsor decision 2026-09-22: summarised records, not a stub cluster. We implement cryptography, so these are core even though ARCH-0001 NG3 defers the algorithm suite and none of them bears on an open DEC-*. This is the worked example of scope §1: the "bears on a decision" test is a prompt for judgement, not a gate.

All body: nist. Each gets a full summary.md — bibliographic header, maturity, applicability, implementations searched, limits.

document what maturity
FIPS 186-5 Digital Signature Standard — ECDSA, EdDSA, RSA standard
FIPS 204 ML-DSA (Module-Lattice) — approved 2024-08-13 standard
FIPS 205 SLH-DSA (Stateless Hash-Based) — approved 2024-08-13 standard
FIPS 180-4 Secure Hash Standard, SHA-2 standard
FIPS 202 SHA-3 and SHAKE — ML-DSA and SLH-DSA depend on it standard
SP 800-208 Stateful hash-based signatures, LMS/XMSS recommendation
SP 800-186 Elliptic curve domain parameters recommendation
SP 800-57 Pt 1 Rev 5 Key management recommendation
NISTIR 8610 Additional signature schemes, round 2 status informational — stub is fine
FN-DSA (FALCON) forthcoming FIPS stub with locator; nothing to summarise yet

FIPS 186-5 is the PROC-0002 stage 8 worked example the sponsor named: generate an implementation from the specification, then verify it. Its test vectors have a real publisher source — NIST CAVP/ACVP — which satisfies the stage 8 rule that vectors come from the source or its publisher and are never generated. If the student cannot find CAVP vectors for the scheme they implemented, that is a stage 10 failure, not an acceptable outcome.

Post-quantum signatures are in the set deliberately. A signature-centric project in 2026 that has not read FIPS 204 and 205 will be asked why.

Parked — deliberately out of scope

id task why
T-090 WP4 — OpenPGP introducer import Out of scope this semester (PLAN-0001 §2)
T-091 WP5 — X.509 import Out of scope this semester
T-092 Transparency service / receipts R-O-04 is Could; not in the demo floor
T-093 Library federation across peers Design and document only; do not build
T-094 Nested threshold subjects v2